Setting Up a Project for Analyses
Both the Schedule Risk Assessment and Sensitivity Analysis require, at a minimum, the following to be done before analyses are be performed:
-
Key Events/Milestone which results will be calculated towards must be flagged “Yes” in a designated flag field
-
Best-Case and Worst-Case duration estimates must be entered in designated duration fields on tasks logically preceding flagged key events
The fields used in your project for this data can be selected from the Instructions & Setup tab of the Schedule Risk Analysis tool: