After clicking Run SRA, the results are recorded in a table on the page named SRA Results. If the user selected more than one SRA Focus item in the project, each of those items will appear in the drop-down list named SRA Focus Item. Each time the user selects a SRA Focus Item the table showing SRA Date, Occurrences (number of times that date was determined by the SRA model), % Probability (the likelihood of completing the schedule exactly on a particular date) and the % Cumulative Probability (the likelihood of completing the schedule on or before a particular date) is populated. The button named Export to Excel and the option named Add Chart provide an Excel workbook based report of the data in the results table.
A list of items in the Schedule flagged as SRA Key Events. When an SRA is performed, the effect of SRA modeling and simulations is calculated for these items. Selecting items from this list shows results that correspond to the selected item.
Results of the Analysis respective of the selected SRA Focus Item are shown in this table. These results can be exported to Excel for further analysis.
The Mean (or average) is the weighted mathematical average of the dates in the results table. When calculating the mean value, each date in the table is counted once for each occurrence of that date to compute the weighted average of all the dates in the results table.
Std Dev (Standard Deviation from the mean) is a measure of how “spread out” the dates are in the results table. Standard Deviation calculations are also weighted by the number of times a date occurs in the results table.