No Baseline

 
What gets flagged by the Audit
A Task, Milestone or Summary that has "NA" in the Baseline Start or Baseline Finish field in Microsoft Project.
 
Why does it matter if items in the project have No Baseline?
Baseline dates in a schedule are useful for comparing current schedule dates, durations, resource assignment information to original (baseline) values.  Baseline values enable cumulative schedule variance analysis.
 
Resolving No Baseline
 
What Else to Consider
Baseline values in a project are used for other SSI Audits and reports.  The Audits named Start or Finish Late to Baseline, for example, can only be performed on tasks that include baseline values.  The SSI Analysis Tool set includes a report named Program Performance Rate Report which relies on baseline data for its analysis.