Start or Finish is Late to Baseline

 
What gets flagged by the Audit
A Task with a Start/Finish date that is later than its baseline Start/Finish
 
Why does it matter if items in the project have Start/Finish Late to Baseline?
Tasks with Start/Finish dates later than their baseline are carrying a schedule variance and may be contributing to late deliverables or increased cost, scheduled or technical risk on the project.
 
Resolving Start/Finish Late to Baseline
 
What Else to Consider
The DCMA 14 Point Assessment tests for Baseline Execution Index (BEI)
BEI: The ratio of the number of tasks completed to the number that should have been completed (per the baseline dates) by the status date. BEI should be > .95