Because the Critical Path Test is unique to the other audits, the audit can be expanded to show more details of how the tool came to the result. For more information on how the Critical Path Length Index is calculated, see this page.
<TODO : Control Name>
The first two lines will show the Unique ID and the name of the task that the tool ran the critical path to for the Critical Path Test and Critical Path Length Index.
The total amount of days (displayed in standard working days) of duration the path spans from the start of the earliest task on the path to the finish of the path focus item.
The total amount of float the focus item of the path has as calculated by Microsoft Project.