Tasks With Negative Slack (Also Called Negative Float)

 
What gets flagged by the Audit
A Task or Milestone with a value less than zero in the Microsoft Project column named Total Slack.
 
Why does it matter if items in the project have Negative Slack?
Negative Slack (Float) means that tasks do not start or finish in time to meet one or more critical date in the project. 
 
What Else to Consider
The 14 Point Assessment tests for "Negative Float"
Negative Float: Total number of activities that are incomplete and have float less than zero working days.
 
Resolving Negative Slack
 
What Does Negative Float Looks Like in a Project?
 
Example 1 - Task Finish does not support a key due date or deliverable in the project
In this example, The combined duration of the sequence of tasks (Task 1 and Task 2) does not support the due date for Milestone C.  This example is simplified to show a direct relationship between the tasks and the due date.  In most cases, negative slack flows through many layers of task dependencies.  The SSI Critical Path Method analysis tool is a good way to find and resolve negative slack in  a project.
 
Example 2 - Negative Slack condition resolved
This example shows one possible solution to resolve the negative slack condition shown in example 1.  In this case, Task 1 and Task 2 are now done in parallel rather than in series.  Since working in parallel shortens the overall duration required to perform both tasks, they now finish 1 day earlier than the due date for Milestone C and the negative slack is removed.