Structured Solutions Performance and Earned Value Tools includes built-in Earned Value reporting using project data. Data showing the Plan Value (aka PV or BCWS), the Earned Value (aka EV or BCWP) and Actual Value (aka AV or ACWP) can be determined by Task Days, Task Work or Task Cost.
When Using Task Days as the EV Unit of Measure, SSI Tools reports the days of work scheduled through a reporting period vs. days of work performed (using the Baseline Duration as the basis) and the actual days taken to perform tasks in the schedule.
When Using Task Work as the EV Unit of Measure, SSI Tools reports the hours of work scheduled through a reporting period vs. hours performed (using the Baseline Hours as the basis). The Actual Value for work hours can be taken from Microsoft Project or it can be imported and held outside Microsoft Project. Work hours can be reported at the Work Package level or rolled up to the Work Package Parent level.
When Using Task Cost as the EV Unit of Measure, SSI Tools reports cost values scheduled through a reporting period vs. cost performance (using the Baseline Duration as the basis). Actual costs can be taken from Microsoft Project or imported and held outside Microsoft Project. Costs can be reported at a Work Package level or rolled up to the Work Package Parent level.