Deltek Cobra™ Transaction File Generator

 
Project Setup for Earned Value Integration with Deltek Products
Many data elements in a project schedule can be shared with popular Earned Value Management Systems (EVMS) like Deltek Cobra™.  Planned Value (PV or BCWS), for example can be taken from the Baseline values in a schedule.  Likewise, Earned Value (EV or BCWP) can be derived from the completion or partial performance of scheduled tasks.  Finally, the remaining work, cost and duration in a schedule is an excellent basis for the Estimate to Complete (ETC) in an EVMS.  To ensure exact traceability between a project schedule and the EVMS, SSI’s Performance vs. Baseline tools includes Transaction and Import file generators for two popular Earned Value Management Systems.
 
 
 
 